INTRODUCTION

Software metrics are an important means to measure the quality of both the development processes and software systems. Improvement reference models such as CMMI require that software development organizations build up abilities to systematically apply metrics to support project management [1]. Based on quantifiable metrics process managers are able to identify processes that contribute to project success or failure. Hence, metrics are a necessity for objective process optimization. However, it is often difficult to integrate measurement values from a large variety of dif-ferent software systems used in software development pro-jects.

Resulting in the different application scenarios for dash-boards and measurement systems (strategic, analytical, or operational [2]) modern measurement systems use new inte-gration approaches. Most recently considerable research was devoted to using service oriented (SOA) and agent based architectures for measurement systems [3]. New loosely coupled integration architectures are researched in the area of enterprise architecture integration (EAI) [4], [5], [6], [7], [8], [9]. Unfortunately, these ideas are not systematically used in measurement infrastructures. Most of the solutions found in the industry right now are based on BI (Business Infor-mation) systems. However, all of the proposed solutions (even the new SOA and agent based approaches) use a cen-tral database or system to store and integrate the measure-ment data. Hence, they suffer from well known centralized integration problems; like the need for a common data sche-ma to integrate different applications. Additionally, not every data should or can be measured (and stored) by means of relational data schemata [10].
In this paper we propose the central requirements for a loosely coupled architecture blueprint of an Enterprise Measurement Infrastructure (EMI) that is aligned with the needs of the different measurement stakeholders as well as the ISO 15939 measurement model. Additionally, the pro-posed infrastructure uses federalist data storage and meas-urement systems to overcome the weaknesses of a central measurement repository.
The following chapter II introduces a typical application scenario for an enterprise measurement infrastructure. This is based on an example taken from our industrial experience. Based on this example we derive three distinct stakeholders with different requirements to the infrastructure in chapter III. Based on this we investigate existing integration and measurement infrastructures in part IV. Chapter V explains in detail the architecture and components of the proposed federalist enterprise measurement infrastructure. Chapter VI provides first experiences with the infrastructure. The paper is concluded in chapter VII.

II. APPLICATION SCENARIO

Project managers and other cross sectional roles in large organizations typically require a lot of information from different systems. For example they are required to control the budget, schedule, costs, quality, requirements, tests, risks and so on. All these control tasks lead a large variety of information needs for the project manager. The answer to a single information need can often be derived from a set of information stored in a certain repository. Different types of information are typically stored in different repositories and often even the same type of information is stored in various repositories. From our experience this problem is not only limited to large organizations. Even project managers in medium sized organizations may need to look into five dif-ferent Change Request Management (CRM) systems (prod-uct development, service, custom solutions, and customer issue tracking (products and custom solutions)) to gather all relevant information.
The following example is used to understand the re-quirements from a business point of view and aligns the different parts of the enterprise measurement infrastructure. We assume a company that established an ISO 15939 com-patible measurement process. In this company projects typi-cally last for a year. A project manager needs to keep a close eye on the budget of the project, the schedule, the overall quality and the risks of the project. She likes to utilize a measurement dashboard that provides charts for the devel-opment of the measurers per month.
The base data for the dashboard is stored in different sys-tems and the data derived from the systems is not uniform. The initial budget (measured in person days) and schedule (measured in calendar days) is stored in a procurement man-agement system per work package. Hence, the budget for the complete project is a sum of all the budget of all work pack-ages assigned to the project. The overall schedule can be derived from the work packages as well. The project utilizes a Change Request Management (CRM) system to store the requirements which are associated to work packages. This system also keeps track of the working hours per require-ment. The sum of all the time spend on the project can there-fore be derived from the work packages in the CRM system. The current schedule can be derived from these work pack-ages as well using a project management tool. The overall quality of the project is monitored using a tool for static source code analysis that measures metric and rule viola-tions. Additionally, the amounts of errors in the system (which are stored in a different CRM system) are used to monitor the overall quality as well. The project manager might want to filter the errors according to their priority (only high priority errors or all errors). The risks are stored in a spreadsheet which is updated regularly and when address-ing certain risks.
This very simple scenario already shows five different systems (procurement management system, project man-agement tool, task CRM system, error CRM system, risk spreadsheet) that need to be integrated to provide measures for the dashboard.

III. REQUIREMENTS FOR AN ENTERPRISE MEASUREMENT INFRASTRUCTURE

The measurement infrastructure needs to address the needs from different stakeholders. After carefully examining the literature and based on our experience we identified the following three main stakeholders:

  •  Measurement Customer
  •  Developer
  •  Operator

Each of these stakeholders provides a unique and specific set of requirements regarding the architecture and the pro-vided functionality of the underlying measurement infra-structure. First we investigate the requirements of the meas-urement customer which holds the main set of functional requirements. Later the developer and operator roles add mainly non-functional requirements for the measurement infrastructure.

Measurement Customer

A project manager is a typical example of a measurement customer. She is interested in the actual status of her project and does not care (and should not!) about the way the data is collected or metrics are calculated. Like in the example above, measurement customers have a brought variety of information needs. Unfortunately, the answers to the differ-ent information needs are stored in various repositories. The scenario introduced above includes different systems for budget, scheduling, tasks and risk information. The resulting central requirement of the measurement customer for an EMI is the integration of these systems in a way that a compre-hensive calculation of metrics is possible.
To achieve this goal, the infrastructure has to cope with the heterogeneity of those systems. Heterogeneity appears on various levels of a software information system. Wache et al. [11] define structural and semantic heterogeneity of data. Structural differences lead to the problem of schema-mapping, a quite well known field of research in the database community [12]. Hence, data heterogeneity is challenging for a successful integration of those systems as well.
Additionally, measurement customers demand correct and up-to-date data because old or incorrect data lead to wrong conclusions and wrong decisions. Hence, an EMI should provide mechanisms that guarantee a fast recognition and processing of relevant events inside the system land-scape. Additionally, this requires a robust and highly availa-bility infrastructure.
Our experience with many industry partners shows that the information needs of measurement customers often change over time. For example development tools and sys-tems are replaced by other tools or systems (tool evolution). Of course, the new tools and systems need to be integrated in the infrastructure. Additionally, processes and organization schemas of enterprises often evolve as well. Especially reor-ganizations lead to new and changed responsibilities of indi-vidual measurement customers and roles which inevitably lead to changes in information needs. Concluding from this, an important requirement for an enterprise measurement infrastructure is to support the evolution of metrics, integrat-ed systems, and visualizations.

Developer

The developer needs to implement metrics, visualizations and tools to gather data. The infrastructure needs to support the developer with a clear structure and concepts for all spe-cific tasks. The task to integrate a new system into the infra-structure to gather its data is completely different from the implementation of a

Operator

This role is often ignored while building and conceptual-izing a measurement system or measurement infrastructures. The operations department has two main responsibilities. First, it has to guarantee that all systems are working inside their operational parameters. This requires a dedicated set of operation tools as part of the infrastructure. The infrastruc-ture should at least provide or support a monitoring tool which allows analyzing the amount of data that is transported and stored in the infrastructures components. Second, the operations department has to solve upcoming problems in the infrastructure without disturbing the integrated systems as these systems are often of crucial importance for the com-pany. The operation department is also responsible for the alignment of the system landscape of the organization. Hence, the infrastructure should be compatible with service oriented architectures found in modern organizations.

Requirements

The sections above motivate the following main func-tional and non-functional requirements for an enterprise measurement infrastructure:
R1. Integration of heterogeneous systems to provide the basis for different metrics and visualizations.
R2. Fast and up-to-date recognition and update of the metrics on a change in an integrated system.
R3. Clear separation of system integration, calculation and visualization.
R4. Be robust to avoid a complete system failure if a small part of the system fails. Additionally, the fail-ure of the infrastructure should not result in a failure of the integrated systems.
R5. No central database to store the measurement values.
R6. No central data schema to avoid schema-mapping problems.
R7. Support evolution of metrics, integrated systems, and visualizations.
R8. Offer dedicated operation tools.
R9. Be compatible to Service-Oriented-Architectures.
This set of requirements will inevitably lead to a loosely coupled federalist infrastructure.

IV. EXISTING INTEGRATION ARCHITECTURES AND MEASUREMENT INFRASTRUCTURES

The integration of heterogonous data sources is the main requirement of an enterprise measurement infrastructure. Throughout the last decade several approaches have been proposed to deal with the emerging problems faced by de-velopers and architects of dealing with heterogeneous sys-tems and software landscapes. In the following we present and analyze four existing types of enterprise application integration approaches and distributed measurement infra-structures based on the proposed set of requirements.

File based integration

The simplest integration approach uses files to exchange data between applications. One application exports the data needed by another as a dedicated file. This file is imported by the other application and processed. This form of integra-tion has certain disadvantages. Most importantly there is no real communications between the applications. Additionally, the export and import of data has to be synchronized. This directly violated the requirements R1, R7, R8, R9, and most importantly R2.

Common Database

This integration approach uses a common database for all integrated systems. This provides a low latency to recognize and process relevant events. The main drawback is the ne-cessity of an additional database management system. Suc-cessful implementations of this integration type are data warehouse systems. They provide an integrated database organized in a star schema [13], which includes multi-dimensional aggregated data cubes.
Integration via a common database or a data warehouse is the most common used integration approach chosen by re-cent measurement systems like Rational Insight. Hackystat and sonarqube are other examples for measurement tools that use a common database to integrate measurement data. However, as these systems are based on centralized data bases they directly violate requirement R3. Additionally, they are not able to guarantee requirement R2 and R7.

Service Oriented Architecture

Service-Oriented-Architecture (SOA) also offer a com-mon used infrastructure pattern for integration solutions. Systems following the service-paradigm [14], [15] provide a stable self-describing interface for accessing internal data and functionalities. Web services are a prominent example for service-based software systems, which uses XML or JSON over HTTP for their communications. Kunz et al. [16] propose a measurement infrastructure based on SOA-inspired service center. Even thought SOA based integration is quiet common a pure SOA solution typically does not provide the required set of operation tools. Hence, this vio-lates requirement R8. Additionally most of the integration solutions use SOA only for the communication between the visualization clients and a central data base server which violates requirement R5 and R6.
Enterprise Information Integration (EII) is a special case of SOA based enterprise application integration. The main goal of EII is to avoid a central database [17]. EII adds a central query processor to an infrastructure of loosely cou-pled services. This central processor divides a query into sub queries to the services and aggregates their results. Even though this is an elegant solution to avoid a central database it violates requirement R4 and since the central processor needs to wait for all the sub queries to finish before returning an aggregated result it can take a while before the system answers which violates R2. Additionally, this still requires a central data schema in the query processor which violates requirement R6.

Agent based integration

Some modern integration approaches use agents to communicate between different applications [18], [19]. Agents where first used in artificial intelligence systems [20]. An agent acts in a certain environment, uses sensors to get information
about it, and can use this information for its decisions. Wille and Dumke et al. propose agent based measurement tools [6], [21]. Even though agent based systems satisfy
a large subset of the requirements they violate some of them. For example they are not compatible with SOAs. Additionally, they cannot provide central monitoring functionalities on
their own because they are loosely coupled and are often hard to integrate into existing or new systems. Hence, agent based systems violate requirements R7, R8, and R9.

V. ENTERPRISE MEASUREMENT INFRASTRUCTURE (EMI) - ARCHITECTURE AND COMPONENTS

Fig. 1. Enterprise Measurement Infrastructure (EMI) components, layers, data flow, control relations, and monitor/use relations

Based on the requirements and typical usage scenarios we propose a layered architecture blueprint for the architecture of an enterprise measurement infrastructure which is depicted in Fig. 1. The information needs of different measurement customers are addressed by specialized analysis or dashboard tools in the Visualization Layer. The actual data needed to calculate metrics is provided by different systems in the Data Provider Layer. These systems are connected to the infrastructure using dedicated data adapters. Often visualization tools require complex and aggregated information besides pure base values. This information is produced and provided by specialized components in the Calculation and Storage Layer. The Data Transport Layer realizes a common communication infrastructure for all components of the Calculation and Storage Layer and of the Data Provider Layer. The Operations Layer contains components required to operate and monitor the complete infrastructure. In the following
we explain the core concepts of the EMI architecture.

Dataflow

The EMI data flow depicted in Fig. 2 is based on the ISO 15939 data flow. There measurement data always flows from base measures to derived measures which are then combined in an analysis model to form an indicator that answers a particular information need. In the EMI we added important extensions, since even base measures (provided by data adapters) can form indicators (e.g. data from a tool like Sonar). Most importantly, derived measures can not only use base measures but the results of other derived measures as well as a combination of the two. ErrorDensity as defined in (1) is a typical example:


To calculate this metric the respective metric kernel needs the current NumberOfErrors and the OverallLinesOfCode. Often, lines of code are provided by a code analysis tool like Sonar. However, these systems typically only count lines of code on a component or build fragment level. To calculate the overall ErrorDensity another metric kernel needs to sum up all the lines of code values from all the build fragments or components to provide a new derived measure OverallLinesOfCode. The NumberOfErrors could be calculated by a CRM metric kernel. This example shows the need of a circular data flow between different metric kernels.

Fig. 2. Measurement and data flow in the EMI

The Measurement Cache located in the Calculation and Storage Layer is a central infrastructure component. It stores all measurement values so they are immediately accessible for visualization components. This also allows the visualization components to directly access base measures if needed. However, the tradeoff of this architectural decision is that the visualization components have to use the stored values.

Data Transport: Enterprise Metric Data Bus

The Enterprise Measurement Data Bus (EMDB), an implementation of an Enterprise Service Bus ([15], [22]), needs to transport the measurement values. Either from a Data Adapter (Base Measure) or from a Metric Kernel (Derived Measure) to all the Metric Kernels and the Measurement Cache of the system.

Fig.3. Concept of the EMDB (Notation by Chappel [5])

The main concept of the EMDB, a publish/subscribe channel, is depicted in Fig. 3. It also shows two Data Adapters (as generic endpoints) and a Metric Kernel (as a Java API client). The messages that are broadcasted over the channel are of type EMDB Message (or a subtype of this). The next section describes these messages types.

EMDB Measurement Messages

The main design principles for the EMI are separation of concern and loose coupling. Hence, metric kernels and data adapters need to be completely separated. A metric kernel just needs to know what measures it requires for its calculations. The data provider just provides specific measures (values) for specific entities (Entities of Measurement – EOMs). Consequently the messages send over the EMDB need to inherit from a general EMDB Message type (see Fig. 4) which just defines three important attributes:

metricRefId represents the identifier (name) of the measure. We propose using a name space schema for the identifiers like
{globalNamespace}.{msgClass}. {msgSubClass}*.{metric}.
An example would be emi.crm.NumberOfErrors or emi.ev.ev or emi.ev.pv as well as emi.ev.cv for the Earned Value Analyis metrics earned value, planed value, and cost variance. This identifier is used by the metric kernels to filter the EMDB messages according to their measurement requirements.

eomId is the identifier of the EOM. It is used to provide a brought variety of measures for the same entity. The data providers typically use an internal eomId from the base systems which they adapt. The metric kernels typically reuse the eomIds from the base measures. The domain synonym repository in the operations layer can be used to build groups of eomIds. This is necessary if different systems which are adapted to the EMI use different identifiers for the same business entity.

value represents the actual measurement value. It is designed as a string to allow a brought variety of values to be transported over the bus instead of just numerical values.

Fig. 4. Base message type hierarchy

Fig. 4 depicts the general EMDB Message with two specialized messages (CRM Message and VCS Message). The general EMDB Message can be extended by every data adapter or metric kernel that is connected to the EMDB to form specific messages that include additional information required by specific metric kernels. In general the data provider should include as much additional information with the message as possible to give the metric kernels as much additional information (for example for filtering) as possible. The CRM Message for example requires additional ticketId and status attributes. This information is useful for specialized metric kernels like our RIFFLE3 Kernel which analyses and provides ticket flows from CRM systems.

Data Provision Mechanisms

The heterogeneity of the systems that are integrated into the infrastructure calls for flexible data provision mechanisms. We investigated three core provision concepts: Push-Forward, Pull-Forward, and Invoke-Push. We describe the main ideas and possible application scenarios in the following subsections.

Push-Forward

Fig. 5. Concept of the Push Forward data provision mechanism

The Push-Forward data provision mechanism guarantees the best latency between change event in the adapted system and the visualization. The sequence diagram in Fig. 5 shows the flow of interactions. Because a plug-in mechanism in the adapted system is needed, a custom build EMI plug-in is then able to hook onto the desired change events in the adapted system. The system calls the plug-in on every data change event. Then, the plug-in creates a (specialized) EMDB message and adds specific data to the message. The message is send to the EMDB using a standard JMS Message Gateway. The data is then transported to the metric kernels and the measurement cache. Hence, the visualization components could immediately update the visualizations to reflect the new data.

Pull-Forward

Fig. 6. Concept of the Pull-Forward data provision mechanism

Standard BI (Business Intelligence) systems use scheduled jobs (called ETL – Extract Transform Load) to derive data from adapted systems. The Pull-Forward data provision mechanism is inspired by these ETL jobs. Fig. 6 shows the sequence of messages. The needed EMI Extract Tasks are triggered by a scheduler who is configured to a certain interval like every minute, hour, or day. The tasks then retrieve the changed data from the systems. It should then extract the unique data chunks from the retrieved data and create a message for every chunk which is then send like push forward.

Even though this provision mechanism is inspired by the most popular mechanism – ETL – it has some strong weaknesses. The most important one is latency which increases dramatically. As a result the data in the visualization is only as up to date as the latest pull interval. One solution would be to reduce the pull intervals to a minimum. However, pulling data from a system typically generates a high load in the system. Therefore, shortening the intervals will lead to performance degeneration in the adapted systems. Another weakness of this solution is the increased effort to implement the data providers.

Invoke-Push

Fig. 7. Concept of the Invoke-Push data provision mechanism

The data stored in the adapted systems typically relate to each other. For example a good practice in software development is to tag a commit into a version control system (VCS) with the task number of a task in a change request management system (CRM). The number of changed files per task could be used as a complexity measure for the task. Additionally, the number of changed lines of code could be used to normalize the effort for a task. Of course, every commit alters the number of changed files for a task. Hence, after every commit a special data adapter needs to send a new message to the EMDB containing additional information to the task. This then allows a special metric kernel to calculate the two measures.

Fig. 7 shows the sequence diagram of the Invoke-Push data provision mechanism which enables EMI developers to implement a special data adapter for the described situation. A special EMDB Message Listener is invoked whenever it receives a certain type of message. It then pulls data from the adapted system (for example the task from the CRM). The data is then packed into a new (specialized) EMDB message and pushed to the EMDB. This mechanism also enables a combination of Push-Forward and Pull-Forward. For example, a VCS message could be used to pull data from a changed spreadsheet file in the VCS. 

 Communication between Metric Kernels and Visualization

The measurement customer typically would like to alter some details in the metric calculation to answer more detailed or slightly tailored questions. For example the question “Are we able to address all bugs?” could be answered by the number of open bugs in a CRM system. If the project is closing in to a release date this question is typically slightly tailored to the question “Are we able to address all important bugs?” which is answered by the number of open bugs in the top categories (priority one and two).

A dashboard should allow a tailoring for these specific situations. The change in the measurement needs to be reflected by the metric kernel. This could either provide both of these metrics or the visualization component could talk directly with the metric kernel and alter the calculation of the specific metric which is feeding a certain diagram. There exist good arguments for both solutions. Hence, the EMI should allow both solutions. 

Two metrics could be easily implemented in a specific metric kernel and could then feed the results back to the EMDB to allow a dashboard to access the values via the measurement cache. This solution is very elegant because it only requires the dashboard to fetch the data from the measurement cache. However, it generates additional effort in the implementation of the metric kernel because this needs to generate more derived measures. Additionally, it can lead to an explosion in the number of metrics which are communicated over the EMDB which could lead to difficulties in the maintenance and operation of the EMI. Also, this makes the measurement cache a central part in the EMI which contradicts the idea of a federalist infrastructure.

The direct communication from a dashboard to a metric kernel requires additional communication flows in the EMI (the control arrows in Fig. 1). This also increases the complexity in the configuration of the dashboard because it now needs to take the (service) source of a metric into account. However, these problems can be solved by a good and flexible framework for the communication between the metric kernels and the visualization components. We propose a solution in which the metric kernels and the dashboard can exchange instances of variability models for each metrics. These variability models include the variability points and variants for each metric. The measurement customer can then change these variability points and tailor the metrics to her specific needs.

REFERENCES

[1] C. P. Team, “CMMI® for Development, Version 1.3 CMMI-DEV, V1.3,” 2010.
[2] S. Few, Information Dashboard Design: The Effective Visual Communication of Data. O’Reilly Media, Inc., 2006.
[3] M. Kunz, A. Schmietendorf, R. R. Dumke, and C. Wille, “Towards a service-oriented measurement infrastructure,” in Proc. of the 3rd Software Measurement European Forum (SMEF), 2006, pp. 197–207.
[4] S. Architecture, “Combining Service-Oriented Architecture and Event-Driven Architecture using an Enterprise Service Bus,” no. April, pp. 1–8, 2006.
[5] D. A. Chappell, Enterprise service bus, 1st ed. O’Reilly Media, Inc., 2004.
[6] R. R. Dumke, “Software-Messung und -Bewertung - Eine Bilanz.” 2012.
[7] K. Umapathy, S. Purao, and R. R. Barton, “Designing enterprise integration solutions: effectively,” European Journal of Information Systems, vol. 17, no. 5, pp. 518–527, 2008.
[8] S. Aier and R. Winter, “Fundamental Patterns for Enterprise Integration Services,” International Journal of Service Science Management Engineering and Technology IJSSMET, vol. 1, no. 1, pp. 33–49, 2010.
[9] T. Puschmann and R. Alt, “Enterprise Application Integration - The Case of the Robert Bosch Group,” vol. 00, no. c, pp. 1–10, 2001.
[10] R. D?browski, K. Stencel, and G. Timoszuk, “Software is a directed multigraph,” Software Architecture, pp. 360–369, 2011.
[11] H. Wache and T. Voegele, “Ontology-based integration of information-a survey of existing approaches,” IJCAI--01 Workshop: Ontologies and Information Sharing, pp. 108–117, 2001.
[12] P. a. Bernstein and E. Rahm, “A survey of approaches to automatic schema matching,” The VLDB Journal, vol. 10, no. 4, pp. 334–350, Dec. 2001.
[13] S. Chaudhuri and U. Dayal, “An overview of data warehousing and OLAP technology,” ACM Sigmod record, no. March 1997, 1997.
[14] M. P. P. and D. Georgakopoulos, M. P. Papazoglou, and D. Georgakopoulos, “Service-Oriented Computing,” Communications of the ACM, vol. 46, no. 10, pp. 24–28, 2003.
[15] M. P. Papazoglou, P. Traverso, S. Dustdar, and F. Leymann, “Service-Oriented Computing: a Research Roadmap,” International Journal of Cooperative Information Systems, vol. 17, no. 02, pp. 223–255, Jun. 2008.
[16] M. Kunz, A. Schmietendorf, R. R. Dumke, and C. Wille, “Towards a service-oriented measurement infrastructure,” pp. 197–207.
[17] A. Halevy, N. Ashish, and D. Bitton, “Enterprise information integration: successes, challenges and controversies,” in Proceedings of the 2005 ACM SIGMOD international conference on Management of data, 2005, pp. 778–787.
[18] R. Kishore, H. Zhang, and R. Ramesh, “Enterprise integration using the agent paradigm: foundations of multi-agent-based integrative business information systems,” Decision Support Systems, vol. 42, no. 1, pp. 48–78, Oct. 2006.
[19] M. Wooldridge, “Intelligent Agents: The Key Concepts,” in Proceedings of the 9th ECCAI-ACAI/EASSS 2001, AEMAS 2001, HoloMAS 2001 on Multi-Agent-Systems and Applications II-Selected Revised Papers, 2002, pp. 3–43.
[20] S. J. Russell, P. Norvig, J. F. Candy, J. M. Malik, and D. D. Edwards, Artificial intelligence: a modern approach, Third Edit. Upper Saddle River, NJ, USA: Prentice-Hall, Inc., 2010.
[21] R. R. Dumke, R. Koeppe, and C. Wille, Software Agent Measurement and Self-Measuring Agent-Based Systems. 2000, pp. 1–44.
[22] M.-T. Schmidt, B. Hutchison, P. Lambros, and R. Phippen, “The Enterprise Service Bus: Making service-oriented architecture real,” IBM Systems Journal, vol. 44, no. 4, pp. 781–797, 2005.